Navillus Inc

Project Spotlight

One Vanderbilt

Delivering the concrete superstructure for Midtown Manhattan's tallest office tower, built directly above one of the world's busiest transit hubs.

1,401 ft
Tower Height
$140M
Contract Value
1.7M SF
Total Area
74,000 CY
Concrete Placed
Project Overview

A Supertall Achievement Above Grand Central

One Vanderbilt is a 1,401-foot supertall office tower at the corner of 42nd Street and Vanderbilt Avenue in Midtown Manhattan. Developed by SL Green Realty Corp. and designed by Kohn Pedersen Fox Associates, the tower stands as one of three landmarks that define Manhattan's skyline alongside the Chrysler Building and the Empire State Building.

Navillus served as the concrete contractor, executing large-scale cast-in-place concrete operations for the tower's superstructure, concrete core, vertical elements, and elevated placements. The scope also included all cast-in-place elevator lobby slabs, concrete on metal deck slabs, and stairs. The project demanded exceptional coordination, with construction taking place directly above the active Grand Central Terminal rail infrastructure and one of the city's busiest pedestrian corridors.

Client / Owner
SL Green Realty Corp.
Construction Manager
AECOM Tishman
Architect
Kohn Pedersen Fox Associates (KPF)
Structural Engineer
Severud Associates
MEP Engineer
Jaros, Baum & Bolles
Project Duration
2017 to 2020
Project Location
1 Vanderbilt Ave, New York, NY 10017
Challenges and Solutions

Building Above a Living Landmark

Challenge
Construction Above Active Rail Infrastructure

One Vanderbilt was built directly adjacent to and above the active Grand Central Terminal, including railroad tunnels and heavily trafficked public areas. Hundreds of thousands of passengers walked directly beneath the active construction site each day, creating extraordinary safety and logistics constraints.

Solution
Disciplined Sequencing and Safety Planning

Navillus implemented rigorous lift and pour planning, controlled access zones, protective decking, detailed pre-task planning, and engineered solutions to reduce interface risk with adjacent trades and the public realm. A safety incentive program resulted in a notable reduction in safety incidents and near misses.

Challenge
Constrained Urban Site in Dense Midtown

Major concrete operations had to be executed on one of the most constrained sites in Manhattan, with extremely limited laydown, delivery, and access space. Moving and installing massive quantities of concrete, rebar, formwork, and embedded materials required constant logistical problem-solving.

Solution
Advanced Logistics and Coordination

Major concrete placements were executed as tightly controlled operations with detailed logistics planning, access coordination, and quality control measures tailored to the constrained site. Close day-to-day coordination with AECOM Tishman, the design team, and specialty suppliers kept multiple trades working safely and efficiently.

Challenge
Multi-Trade Coordination at Scale

Concrete work had to be coordinated with structural steel erection, formwork cycling, pumping, hoisting, inspections, rebar installation, MEP embeds, and adjacent transit improvement work. The aggressive schedule demanded precision at every trade interface. Throughout the superstructure sequence, Navillus was required to keep concrete operations within a prescribed number of floors of the advancing steel erection floor, making sequencing and trade coordination critical.

Solution
PERI Core Climbing Formwork System

Navillus implemented the PERI core climbing formwork system as part of a broader sequencing and coordination strategy for the superstructure work. This engineering approach allowed steel within the core to advance ahead of the surrounding concrete while enabling Navillus to keep its concrete operations within the prescribed number of floors of the advancing steel erection floor. The system supported the required construction sequence, reduced conflicts at critical trade interfaces, and helped maintain the aggressive project schedule.

Engineering Innovation

Steel-First Erection with Climbing Core System

Navillus used a self-climbing formwork system within the core and hand-set forms from the exterior. The project followed a steel-first erection sequence, with the reinforced concrete core advancing behind the structural steel as the tower rose. Concrete work typically followed within six floors of the active steel erection floor, helping maintain the required construction sequence. Core and shear wall thicknesses ranged from 24 inches to 42 inches, with compressive design strengths of up to 14,000 psi.

This approach supported the required construction sequence and helped maintain the aggressive superstructure schedule through close coordination between concrete and steel operations. The concrete shear walls were further augmented by steel outrigger trusses at three intermediate mechanical levels to help control lateral drift in the structure.

Safety Record

Protecting the Public and the Workforce

Exposure and Risk

The project presented exceptional public and worker safety challenges due to ongoing activity at Grand Central Terminal directly below and adjacent to the work. Heavy concrete placements at height, tower crane and hoisting interfaces, restricted access, and the sheer volume of pedestrian traffic created one of the most complex safety environments on any project in New York City.

Measures Implemented

Navillus deployed controlled access zones, confined space readiness, protective decking, engineered solutions, and close coordination with site safety management. Disciplined sequencing of concrete operations reduced interface risk with adjacent trades and the public realm. Navillus also developed and implemented a safety incentive program at One Vanderbilt to support the project's overall safety performance. In recognition of this initiative, Navillus was awarded the 2018 BTEA Safety Innovation Award.

74,000
Cubic Yards of Concrete
26,000
Tons of Steel
8,000
Tons of Rebar
4M+
Total Man-Hours
The Navillus team at One Vanderbilt
The Navillus Team at One Vanderbilt
Recognition

Award-Winning Achievement

2018
BTEA Safety Innovation Award
Navillus
2022
Best Tall Building 400m+
CTBUH Awards / Category Winner
2022
Diamond Award for Excellence
Engineering Excellence Awards
2022
Best Tall Office Building
CTBUH Awards / Award of Excellence
Certified
LEED Platinum
Sustainability Certification
Certified
WELL Platinum
Health and Wellness Certification
Project Outcome

One Vanderbilt opened on September 14, 2020 as the tallest office tower in Midtown Manhattan. The $3.1 billion development stands as a major addition to the New York City skyline and a landmark project above Grand Central Terminal. For Navillus, it represents a flagship example of delivering large-scale concrete work on a complex supertall project in a highly constrained urban environment.

$3.1B
Total Development Value
Scroll to Top